AOC 38 Closure

aoc1
aoc2
aoc4
Client: Private Client
Location: Simsbury, CT

Project Description: TFCI was the general contractor for the closure of two former disposal areas at a processing facility in Simsbury, Connecticut. Site preparation work included extensive clearing, waste relocation, and debris consolidation including several caches of former explosives containing materials. TFCI installed a base sand layer which was covered with an HDPE membrane, drainage geocomposite, and embedded piping system. Vegetative support soil and topsoil were then installed to complete the caps. As all of the work was performed immediately along the fringes of the wetlands, work sequence and stone toe stabilization were critical in maintaining adequate wetlands protection.